More expansionThe company made some calculations, and decided that it would need roughly 140,000 pounds in order to run an optimal profit train on the Canhall-Trendingworth line, the company went into silence, slowly started repaying the loan to lower interest rates and in 1930 and 1931 there was no activity.
However it suddenly pounced back to life in 1932, and maxed out their loan, and bought themselves a shiny new locomotive and rolling stock, costing a total of 141,824 pounds.

This new train would be dubbed the "intercity express", offering blazing fast passenger transport on the Canhall - Trendingworth falls route, with an extra stop in Wundtown, it will also carry a mail wagon, in order to quickly move the amount of mail that was being left behind. The new train was the companies "major weapon" and provided the lucky citizens in selected cities, the chance to travel in complete luxury. The 4-6-2 pacific hauling 3 passenger wagons and a mail wagon, was a true beast of a machine. During it's first round trip, it made a total profit of 11,319, boosting the companies money stash significantly.
For 1933, the company did not do much, they added a mail wagon to the Chadston - Tredingworth Falls train route, and mostly focused on planning additional train routes, including a possible train station expansion at Tredingworth. They also built a bridge for road vehicles at the site of the old road vehicle accident, hoping to fix the problem. The company was also on the lookout for potential towns to add to the train network, and found a suitable candidate, however it would not initially be connected to the rail network, and would rather start off as it's own branch.

The Sardstone - Prendingstone Bay - Wratfingway triangle was selected as a prime candidate, the later two towns would be connected by a bus service, while Sardstone would have a train line going towards Prendingstone Bay, construction would be expensive, but the company deemed the expenses small enough to give the go ahead to construction.
The bus route excluding buses came to around 80,000 pounds cost, but the bus profit per trip was around 300 pounds, and the company had hoped to get 4 buses running on the route by 1935. The goal was achieved at the start of 1934, and the company began plans on building the railroad connection. However the initial costs were shocking.

This small bit of rail, that would cost about 5,000 on regular OTTD, cost me FIFTY THOUSAND, just to give you a general idea of just how batshit insane the prices can be. It was obvious the company would have to take it's time building this, and that it could not be rush, but the investors were sure the connection could be completed.

During april, the company added an extra bus station to both Canhall and Trendingworth falls, and added double deckers to the route, also helping out the bottleneck of passengers at both towns, another further bus station was also built between Canhall and Wundingtown, as the towns actually started joining together, the new buses were far better than the old Model T buses, bringing in a profit upwards of 1,000 pounds a month. In march 1935, the construction was complete, however, the cost was high;


The investors were shocked when the cost came in, excluding the trains, the rail construction alone required nearly 300,000 pounds to be constructed, the train would really have to pull a lot to make it through this, however the potential is there, and the investors hope the train will make a profit of at least 30,000 pounds per year, in order to make this project worthwhile. The train was to be passenger only, and started operating in December 1935, the 4-4-0 Express with 4 passenger wagons cost roughly 110,000 pounds. With the basis of the network being laid down, the company started work on repaying the loan.
However due to the increasing amount of passengers in Nunningley Market and Tredingworth Falls forced the company to build a second platform at Tredingworth, and added an extra train going towards Nunningley market in order to help with the passenger bottleneck at the station. This also forced a doubling of the track going from Wundtown to Tredingworth. However once up, the train helped the station move passengers, and while there still being passengers remaining at the station. Along with this came another station platform at Canhall, with the company starting to build another line towards a small town called Chafield (421) nearby.
Once the line was connected, the company investors decided that they want the newest top of the line train running on it, so the company had to drop down 200,000 pounds for their newest addition to the train fleet, a 4-6-2 Streamliner with 3 passenger wagons and a mail wagon.

More construction happened with Chadston connecting with Wundtown, and a train was added going from Chadston to Canhall, however without stopping at Wundtown. The train is a Pacific 4-6-0 Standard Five, giving a nice balance between cost, speed and power, at a fair price of 68,000. It is running 2 passenger and 2 mail wagons, making it differ from the usual train fleet, and to help the massive amount of mail being left behind at Canhall. The train began operating in September. For the rest of the year the company started paying back as much of the loan as possible, and when 1940 came the company managed to pay of 90,000 pounds of the loan.
1940 main train network overview:
